| 1.0 |
Issue Identification |
Defect Description, Location (Grid/Level), Photos & Specification Reference |
W
H
W
|
ISO 9001:2015 Cl 8.7 |
Clear objective evidence with drawing numbers, grid lines, photo log, and specific breached clause cited |
Consultant QA/QC Inspector |
| 2.0 |
Containment |
Immediate Work Stoppage, Red Tagging & Containment Actions |
H
H
W
|
Project Quality Plan |
Affected area physically isolated or red-tagged to prevent further unauthorized construction |
Site QC Manager & Superintendent |
| 3.0 |
Root Cause Analysis |
5-Whys or Fishbone Root Cause Analysis (RCA) Investigation |
H
R
R
|
ISO 9001:2015 Cl 10.2 |
Systemic root cause identified (personnel, machine, method, material, or measurement) rather than surface symptom |
Contractor QA/QC Manager |
| 4.0 |
Disposition Proposal |
Technical Remedial Proposal: Rework, Repair, Concession, or Scrap |
H
H
W
|
Project Specifications |
Detailed method statement submitted with structural calculations if repair or concession is requested |
Technical Engineering Lead & QC |
| 5.0 |
Consultant Review |
Consultant / Engineer Review and Disposition Approval / Rejection |
R
H
W
|
Contract Conditions |
Disposition formally endorsed or returned for revision by the Consultant Resident Engineer |
Consultant Resident Engineer |
| 6.0 |
Execution of Rework |
Execution of Approved Remedial Work under Direct QC Surveillance |
H
W
S
|
Approved Remedial Method |
Rework executed exactly as detailed in the approved disposition procedure without deviations |
Site Foreman & Contractor QC |
| 7.0 |
Re-Inspection |
Re-Inspection & Verification Testing of Remedial Works (e.g. Core Test) |
H
H
W
|
IFC Drawings / Standards |
100% compliance verified through NDT, core crushing, or survey checks with zero remaining defects |
Consultant QA/QC Inspector |
| 8.0 |
CAPA & Close-Out |
Preventive Action Implementation, Tool-Box Training & Formal NCR Closure |
H
H
H
|
ISO 9001:2015 Cl 10.2 |
Work procedure updated, site teams retrained, and formal sign-offs completed to close the NCR log |
QA/QC Manager, Consultant RE & Client |