| 1.0 |
Document Review |
Concrete Mix Design & Raw Material Mill Certificates Approval |
H
H
R
|
ACI 301 / ASTM C150 / ASTM C33 |
Mix design approved for compressive strength (e.g. C35/45), water-cement ratio <= 0.42, chloride and sulfate limits verified |
Contractor QA/QC & Consultant Civil Engineer |
| 2.0 |
Pre-Pouring |
Survey Setting Out, Axis Coordinates, and Formation Levels |
H
W
S
|
Project Drawings & ACI 117 |
Elevation tolerance within +/- 5mm, grid coordinate alignment within +/- 3mm |
Chief Surveyor & Consultant Inspector |
| 3.0 |
Pre-Pouring |
Rebar Placement, Cover Blocks, and Splice Lapping Verification |
H
H
W
|
ACI 318 / BS 4449 |
100% cover block compliance (minimum 50mm for substructure), lapping length 50d, clean of rust flakes and oil |
Civil QA/QC Inspector & Consultant RE |
| 4.0 |
Pre-Pouring |
Formwork Plumb, Alignment, Cleanliness & Release Agent |
H
H
R
|
ACI 347 / BS 5975 |
Line and plumb within +/- 3mm over 3m; zero pooling of release agent; air-blower cleaning of formwork base |
Site Foreman & Consultant Inspector |
| 5.0 |
Pre-Pouring |
Embedment Items, Waterstops, MEP Sleeves & Box-Outs |
H
H
W
|
Approved MEP Coordinated Drawings |
All PVC/hydrophilic waterstops centered with continuous welds; MEP conduits capped; zero clashes |
MEP Coordinator & QA/QC Inspector |
| 6.0 |
Delivery Inspection |
Slump Flow, Concrete Temperature & Batch Time Verification |
W
W
S
|
ASTM C143 / ASTM C1064 |
Slump within 150 +/- 25mm; temperature <= 32°C (hot weather <= 30°C); batch discharge within 90 mins |
Independent Testing Lab & Site QA/QC |
| 7.0 |
In-Process |
Compressive Test Cylinder Sampling (7-day & 28-day sets) |
W
W
S
|
ASTM C31 / ASTM C39 |
1 set of 6 cylinders per 50m³ or per truck batch group; initial curing under moist condition at 23 +/- 2°C |
Third-Party Lab Technician & QC |
| 8.0 |
In-Process |
Placement, Free Fall Height, and Vibratory Compaction |
H
W
S
|
ACI 309R / ACI 304R |
Maximum free-fall <= 1.5m; poker vibrator inserted vertically at 450mm centers; no dragging of vibrators |
Civil Construction Supt & QC Inspector |
| 9.0 |
Post-Pouring |
Curing Compound Application or Wet Burlap & Polyethylene |
H
W
S
|
ACI 308R / ASTM C309 |
Moist curing initiated immediately after final finishing; continuous wet burlap maintained for minimum 7 days |
Civil Site Engineer & Consultant |