| 1.1 |
Material Verification |
Shutter Plywood Grade, Film Thickness & Steel Soldiers Check |
W
R
R
|
ACI 347 / BS 5975 |
Marine ply 18mm with intact phenolic film; steel walers free of permanent bending or weld fatigue |
Civil QC Inspector |
| 1.2 |
Setting Out |
Kicker Line, Centerlines & Internal Dimensions Verification |
H
W
S
|
IFC Drawings & ACI 117 |
Internal clear dimensions within +/- 3mm of structural design drawings |
Chief Surveyor & QC Inspector |
| 2.1 |
Assembly |
Verticality, Plumbness & Alignment of Wall and Column Forms |
H
H
W
|
ACI 117 Table 4.1 |
Plumb tolerance <= 6mm per 3m height; total accumulated deviation <= 12mm over building height |
Civil Site Engineer & Consultant |
| 2.2 |
Assembly |
Tie-Rod System, Sleeves, Cones & Waterstop Rings for Retaining Walls |
H
H
W
|
Project Technical Specs |
High-tensile tie rods torqued evenly; cast-in waterstop tie-plugs installed on external water-retaining walls |
Civil Foreman & QC Inspector |
| 2.3 |
Falsework & Shoring |
Shoring Tower Bracing, Jack Extensions & Base Plate Bearings |
H
H
W
|
BS 5975 / Approved Falsework Design |
Screw jacks extended <= 300mm maximum; diagonal bracing 100% pinned; sole plates seated on firm soil |
Temporary Works Engineer & QC |
| 2.4 |
Joints & Gaskets |
Form Joint Sealing, Foam Gaskets & Foam Tape for Zero Slurry Leakage |
W
W
S
|
ACI 347 Section 3.2 |
All plywood joints sealed with compressed neoprene foam tape; zero visible gaps at form junctions |
Civil Foreman & QC Inspector |
| 2.5 |
Chemicals |
Form Release Agent Application Uniformity & Surface Dryness |
W
W
S
|
ACI 301 Section 4 |
Non-staining approved release oil sprayed evenly with no puddles, drips, or transfer onto steel rebar |
Site QC Inspector |
| 2.6 |
Final Verification |
Clean-Out Ports Inspection, Debris Flushing & Final Sign-Off |
H
H
W
|
ACI 301 |
Bottom clean-out access windows inspected, debris flushed with pressurized air/water, windows bolted shut |
Civil QA/QC & Consultant RE |